Asda Stores Ltd

Rose has worked with Asda since 1997 following selection into their partnering framework. Throughout this period we have actively contributed to improving speed of delivery and reducing cost through innovation and continuous improvement. Build times for new stores has reduced from 27 weeks (from commencement of steel) to as little as 17 weeks and considerable cost savings have been realised through challenging the brief and value engineering.

Working with other consultants we have developed best practice documents and processes that have facilitated these results including snag free handovers and minimal disruption to trading stores.

To date Rose has successfully completed in excess of 130 projects including new builds, developer shell schemes, extensions, refurbishments and petrol filling stations.